摘 要
本文聚焦于某高速公路 K242 + 500 - K242 + 600 段滑坡整治工程设计,采用抗滑桩支护方案。首先介绍了常见支护方法,包括抗滑桩、预应力锚索、格构锚固结构以及预应力锚索格构梁等,为后续设计提供背景参考。接着详细阐述了边坡概况,涵盖工程整体情况、自然地理条件以及工程地质条件,为设计提供基础数据。在设计思路部分,明确了主要设计方案思路、设计依据资料、设计原则以及设计参数。滑坡体稳定性计算环节,遵循基本原则,采用相应计算方法得出滑坡推力,为抗滑桩设计提供关键参数。抗滑桩设计方法部分,全面介绍了抗滑桩概述、设计要求与内容、荷载确定、计算方法以及具体设计过程,并针对 K242 + 588.41 断面处抗滑桩展开详细设计。工程抗滑桩施工组织设计从施工准备、顺序、质量要求、质量保证措施以及雨季施工保障措施等方面进行了规划。工程抗滑桩监测方案设计明确了监测目的,分别对施工期安全监测和防治效果运营期长期监测进行了安排。此外,还进行了滑坡排水与绿化工程设计,遵循排水设计原则,设计了排水系统,并规划了绿化工程。通过以上综合设计,旨在有效整治该高速公路段的滑坡问题,保障道路安全运营。
关键词:高速公路;滑坡整治;抗滑桩支护;稳定性计算;施工组织设计;监测方案;排水与绿化工程
Abstract
This paper focuses on the landslide remediation engineering design for the K242 + 500 - K242 + 600 section of a certain expressway, adopting an anti-slide pile support scheme. Firstly, common support methods are introduced, including anti-slide piles, prestressed anchor cables, lattice anchor structures, and prestressed anchor cable lattice beams, providing a background reference for subsequent design. Then, a detailed description of the slope conditions is presented, covering the overall engineering situation, natural geographical conditions, and engineering geological conditions, which offer fundamental data for the design. In the design concept section, the main design scheme ideas, design basis data, design principles, and design parameters are clarified. During the landslide mass stability calculation phase, following the basic principles, corresponding calculation methods are employed to obtain the landslide thrust, providing key parameters for the anti-slide pile design. In the part of anti-slide pile design methods, a comprehensive introduction to the overview, design requirements and contents, load determination, calculation methods, and specific design process of anti-slide piles is provided, with a detailed design carried out for the anti-slide piles at the K242 + 588.41 cross-section. The construction organization design for the engineering anti-slide piles outlines plans from aspects such as construction preparation, sequence, quality requirements, quality assurance measures, and rainy season construction safeguard measures. The monitoring scheme design for the engineering anti-slide piles clarifies the monitoring objectives and makes arrangements for safety monitoring during the construction period and long-term monitoring of the remediation effect during the operation period, respectively. In addition, the drainage and greening engineering designs for the landslide are conducted. Following the drainage design principles, a drainage system is designed, and a greening project is planned. Through the above comprehensive design, the aim is to effectively remediate the landslide problem in this expressway section and ensure the safe operation of the road.
Keywords:expressway; landslide remediation; anti-slide pile support; stability calculation; construction organization design; monitoring scheme; drainage and greening engineering
目 录
1 常见支护方法简介
1.1 抗滑桩
1.2 预应力锚索
1.3 格构锚固结构
1.4 预应力锚索格构梁
2 边坡简介
2.1 工程概况
2.2 自然地理
2.3 工程地质条件
3 设计思路
3.1 主要设计方案思路
3.2 设计依据资料
3.3 设计原则
3.4 设计参数
4 滑坡体稳定性计算
4.1 滑坡推力计算的基本原则
4.2 滑坡推力的计算方法
4.3 滑坡推力计算
5 抗滑桩的设计方法
5.1 抗滑桩概述
5.2 抗滑桩设计要求和设计内容
5.3 抗滑桩设计荷载确定
5.4 抗滑桩计算方法
5.5 抗滑桩的设计
5.6 K242+588.41断面处抗滑桩设计
6 工程抗滑桩施工组织设计
6.1 施工准备
6.2 施工顺序
6.4 质量要求
6.5 质量保证措施
6.6 雨季施工保障措施
7 工程抗滑桩监测方案设计
7.1 监测工程的目的
7.2 施工期安全监测
7.3 防治效果运营期长期监测
8 滑坡排水与绿化工程设计
8.1 排水设计原则
8.2 排水系统设计
8.3 绿化工程设计
参考文献
谢 辞