摘 要
招标控制价是根据国家或省级、行业建设主管部门颁发的有关计价依据和办法,按设计施工图纸计算的,对招标工程限定的最高工程造价。招标控制价包括分部分项工程费、措施项目费、其他项目费、规费、税金。建设工程工程量清单是是建设工程招投标工作中,由招标人按国家统一的工程量计算规则提供工程数量,由投标人自主报价,并按照经评审低价中标的工程造价计价模式。表示的是实行工程量清单计价的建设工程的分部分项工程项目、措施项目、其它项目、规费项目和税金项目的名称和相应的数量。
本设计的主要内容为桂林理工大学宿舍楼工程招标控制价编制,工程建筑总面积为4959.53平方米,工程类别为四类工程,抗震等级为三级,抗震设防烈度为7度。根据《11G101-1、2、3图集》和《建设工程工程量清单计价规范》的规则计算出钢筋、混凝土、装饰等各分部分项工程量,此次毕业设计主要为正确独立完成该工程量计算,并进行工程量清单编制工作,包括建筑工程、装饰装修工程、电气工程、给排水工程、消防工程以及各单位工程对应的措施项目,并进行工程概况指标参数分析和工程造价基础指标参数分析。
关键词:宿舍楼;工程量;清单;招标;控制价
Abstract
The bidding control price is calculated according to the relevant pricing basis and methods issued by the national or provincial or industrial construction competent departments, and the maximum project cost limited by the design and construction drawings.The tender control price includes partial project fees, measures and project fees, other project fees, regulatory fees and taxes.The bill of quantities of construction project is in the bidding work of construction project, the tenderer provides the number of projects according to the unified calculation rules of project quantity of the state, the bidder offers the price independently, and the project cost of the low price after evaluation.It represents the name and corresponding number of partial projects, measures projects, other projects, fees projects and tax projects of the bill of quantities valuation.
The main contents of this design are the bidding control price preparation of the dormitory building of Guilin University of Technology. The total construction area is 4959.53 square meters, the project category is four types of projects, the seismic grade is level 3, and the seismic fortification intensity is 7 degrees.According to the rules of reinforcement, concrete, decoration and other parts of quantities. The graduation design is mainly to complete the project quantity calculation, and prepare the bill of quantities, including construction engineering, decoration engineering, electrical engineering, water supply and drainage engineering, fire control engineering and measures corresponding to each unit engineering, and conduct parameter analysis of project overview index and project cost basic index parameters.
Key words: dormitory building; project quantity; list; bidding; control price
目 录
摘 要 I
Abstract II
前 言 1
1.设计说明 2
2.工程量清单的编制 2
2.1建筑工程工程量清单内容和编制特点 2
2.2装饰装修工程工程量清单内容和编制特点 2
2.3电气工程工程量清单内容和编制特点 2
2.4给排水、消防工程工程量清单内容和编制特点 3
3.招标控制价的编制 3
3.1建筑工程招标控制价编制特点 3
3.2装饰工程招标控制价的编制特点 4
3.3电气工程招标制价编制特点 4
3.4给、排水及消防工程工程招标制价编制特点 5
4.工程量清单 5
4.1总说明 5
4.2工程量清单 5
4.3工程量清单编制依据 16
4.4分部分项工程量清单计价说明 16
4.6措施项目清单计价说明 17
4.6其他项目清单计价说明 21
4.7税金计价说明 21
5.招标控制价 22
5.1工程招标控制价总说明 22
5.2单位招标控制价 23
5.2建设项目招标控制价汇总表 24
5.3单项工程招标控制价汇总表 25
5.4单项工程招标控制价汇总表 35
5.5分部分项工程和单价措施项目清单与计价表 46
5.6总价措施项目清单与计价表 49
5.7综合单价分析表 50
5.8其他项目清单与计价汇总表 84
5.9规费、税金项目清单计价表 85
5.10主要材料(设备)数量与计价表 86
6.总结与体会 87
致 谢 88